Kathleen Road widening is moving to the study phase in Polk County. This is a study, not construction.
On Oct 20, the Polk County Board of County Commissioners approved an agreement worth about 2.15 million (2,148,563.40) with Patel, Greene & Associates.
Task 1 is an alignment study of roughly 540 days. It covers widening Kathleen Road from Duff Road to W Socrum Loop Road, plus a new alignment from W Socrum Loop Road to Rockridge Road.
Design plans come back to the board later. About 2 million comes through FDOT's federal Local Agency Program. There is no construction date or construction cost yet.
Do you drive Kathleen Road? Send this to someone who does.
Photo: DanTD / Wikimedia Commons, CC BY-SA 4.0, cropped. Generic stretch of CR 35A. This image is a modified version of the original and is shared under the same license (CC BY-SA 4.0).
Source: Polk County BOCC, File 26-2046